Why a reactor's run length sets the clock in a station blackout

A 2023 study models a 3,250 MW PWR losing all power and finds core damage 15.4 h after a week of operation but 9.7 h after 1,350 days. We rebuild that spread from the Way-Wigner decay heat formula with fibub's decay heat estimator.

When a reactor loses all electrical power, fission stops within seconds but the fuel keeps making heat, and the clock that matters is how long the water lasts. A 2023 study in Frontiers in Energy Research modelled a 3,250 MW four-loop pressurised water reactor through a flood-induced station blackout with the system code RELAP5-3D, and found something a reader can check by hand: the time to core damage depends strongly on how long the reactor had been running. One week of operation buys 15.4 hours; 1,350 days buys only 9.7. This article rebuilds that spread with the decay heat estimator, which uses the same Way-Wigner formula the paper does. For the physics before shutdown, see the neutron diffusion calculator and the point kinetics simulator.

The paper in brief

The authors build a plant model of a generic Westinghouse four-loop PWR (based on Zion Unit 1) and run two blackout scenarios. In the short-term case the turbine-driven auxiliary feedwater pump fails at once: the steam generators dry out after 1.13 h, the core starts to uncover at 1.44 h, and the peak cladding temperature reaches the 1,477 K damage limit at 2.49 h. In the long-term case that pump runs on battery power for about four hours first, which pushes dryout to 7.92 h and core damage to 9.74 h.

They then ask what difference the reactor’s operating history makes, because that history sets how much fission-product inventory has built up. Keeping everything else the same, core damage comes at 15.37 h after one week of operation, 12.47 h after one month, 10.71 h after one year and 9.74 h for the base case of 1,350 effective full-power days. The decay power itself comes from the Way-Wigner relation, P(t)/P₀ = 0.0622 [t⁻⁰·² − (t₀ + t)⁻⁰·²], which is exactly the formula behind fibub’s tool.

Checked with the tools

Everything here is a recomputation from the paper’s own stated inputs (3,250 MW, the four operating histories, the blackout at 100 s) with the tool’s version of the formula. No data are fitted and nothing is simulated.

Step 1: how much heat, and when. One minute after shutdown of a long-running core the formula gives 2.59 % of full power, about 84 MW. One hour after shutdown the decay heat is 34.4 MW for the 1,350-day history but only 25.2 MW for the one-week history: a 37 % difference from the operating time alone, because a week is not long enough to build up the longer-lived fission products. The heat first falls below 1 % of full power after 1.28 h for the long history and after only 26 minutes for the one-week history, and below 0.5 % after 22 h and 3.7 h respectively.

Decay heat after a blackout, by how long the reactor ranDecay heat after a blackout, by how long the reactor ran020406080100100010000100000Seconds since shutdownDecay heat (MW)15.37 h9.74 h1 week1 month1 year1,350 daysfibub.com
Figure 1. Decay heat of the paper's 3,250 MW reactor against time since shutdown, worked out with the Way-Wigner formula in the Decay heat estimator for the paper's four operating histories. The dashed lines mark the core-damage times the paper's RELAP5-3D model reports.

Step 2: the energy budget, which is what actually ends the accident. Boiling water away is an energy problem, not a power problem, so we asked the tool for the energy released between the blackout at 100 s and each core-damage time the paper reports (the tool uses the exact integral of the formula, so this is not a numerical approximation):

Operating history Paper’s core-damage time Decay heat at 1 h Energy released by then Water that much heat boils
1 week 15.37 h 25.2 MW 792 GJ 351 t
1 month 12.47 h 28.8 MW 850 GJ 377 t
1 year 10.71 h 32.9 MW 923 GJ 409 t
1,350 days 9.74 h 34.4 MW 910 GJ 403 t

The four core-damage times differ by 58 %, but the energy released by then differs by only 15 %, and averages 869 GJ, enough to boil about 385 tonnes of water. In other words the accident is governed by a roughly fixed amount of water to be boiled, and the operating history only changes how fast the heat arrives.

Energy released since the blackoutEnergy released since the blackout05001e+305101520Hours since the blackoutEnergy released (GJ)869 GJ on average1 week1 month1 year1,350 daysfibub.com
Figure 2. The same four histories, now as the energy decay heat has released since the blackout (the tool's exact integral of the formula). The dots are the paper's core-damage times; they cluster near 869 GJ, the energy needed to boil about 385 tonnes of water.

Step 3: predicting the paper’s times from that one number. Turning it round, we asked the tool when each history has released 869 GJ. That single number, with no plant model at all, gives 17.9 h, 12.9 h, 9.9 h and 9.2 h, against the paper’s 15.4, 12.5, 10.7 and 9.7 h: the right order, the right spacing, and within 0.4 to 2.5 hours. The one-week case is the loosest, which makes sense, as it is the case where the fixed-budget picture is worst (less power, so more time for the stored heat and the structures to matter).

Check Paper (RELAP5-3D) Decay heat estimator, fixed 869 GJ budget
Core damage, 1 week of operation 15.37 h 17.87 h
Core damage, 1 month 12.47 h 12.87 h
Core damage, 1 year 10.71 h 9.89 h
Core damage, 1,350 days 9.74 h 9.17 h

Step 4: the short-term case is a different problem. Run the same sums on the short-term blackout and the energies are much smaller: 165 GJ by steam generator dryout at 1.13 h and only 313 GJ (about 139 t of water) by core damage at 2.49 h. That is the signature of losing the feedwater at once: the heat is not much higher, but there is far less water to take it, so the same energy budget argument does not carry across scenarios. In the long-term base case, dryout at 7.92 h corresponds to 776 GJ, around 344 t.

One detail worth flagging: the paper labels its 1,350-day base case “infinite”. The formula’s truly infinite history gives 24.8 MW at 10 h against 20.0 MW for 1,350 days, a 24 % difference, so the two are not interchangeable in the hours that matter here.

How we made the graphs

The charts and every number come from scripts/blog-figures/station-blackout-decay-heat-operating-time.mjs in fibub’s public code. It calls fraction (the Way-Wigner decay fraction), energy (its exact integral over an interval), timeBelow (when the heat falls under a level), duration and the latent heat H_FG from src/lib/sci/eng-decayheat.ts, the maths behind the decay heat estimator.

The thermal power, the four operating histories, the 100 s blackout time and the event times are from the paper’s text and tables. The 869 GJ energy budget is our average of the four cases, not a value from the paper, and the step-3 prediction is ours, not the paper’s method.

How we test the maths

On every change to fibub, tests/sci.mjs runs tests/sci-tools/decay-heat.mjs, which pins this tool against SciPy:

  • the decay fraction at 24 combinations of time and operating history, to 1 part in 10¹³ (for example 1.0125 % one hour after a year of operation);
  • the energy integral over 16 intervals against adaptive quadrature, to 1 part in 10⁹, and separately against a 200,000-step midpoint sum;
  • the time to fall below 5 %, 1 % and 0.1 % against Brent root-finding, for four operating histories;
  • New with this article: a 3,250 MW core must give 34.4 MW an hour after 1,350 days of operation and 25.2 MW after one week, and the energy released from 100 s to 9.74 h and to 15.37 h must be 910 GJ and 792 GJ.

Check it yourself

On the decay heat estimator page:

  1. In the Reactor card, type Thermal power before shutdown P₀ (MW) 3250, Time at that power 1350 and set Unit to days.
  2. The Decay heat table reads about 2.59 % (84 MW) one minute after shutdown and 1.06 % (34.4 MW) after one hour, with the water it would boil each hour beside it.
  3. Set Find when heat falls below (% of P₀) to 1: it answers about 1.28 hours. Change Time at that power to 7 days and the same question answers about 26 minutes.
  4. In Energy over your own interval, set From 0.0278, To 9.74 with Unit on hours (that is 100 s to the paper’s base-case core-damage time). The energy released is about 910 GJ, or 2.8 × 10⁵ MW·s per MW of rating.
  5. Change Time at that power to 7 days and To to 15.37 hours: the energy is about 792 GJ, within 10 % of the first answer although the time is 58 % longer.

What researchers can use it for

  • Sanity-check a severe-accident timeline before running a system code: a fixed energy budget and the Way-Wigner integral get the ordering and the spacing of events right.
  • Size an emergency water inventory: the tool gives the tonnes of water boiled per hour directly, so a tank volume turns straight into hours of grace.
  • Show how much the operating history is worth, which matters for shutdown-state and refuelling risk assessments as much as for full-power ones.
  • Plan a sensitivity study: pick the operating times that actually separate the curves, instead of running them all.
  • Teach the difference between power and energy in accident analysis, which is where intuition usually fails.

The fine print

  • Way-Wigner is a rough fit to the fission-product mixture, generally quoted as fair from about 10 s to a few months after shutdown. It carries no actinide or activation heat, and serious work uses ANS-5.1 or a full inventory calculation.
  • Our 869 GJ budget is an average over the paper’s four cases, so step 3 is a consistency check, not an independent prediction. The plant model includes stored heat, metal structures, pressuriser discharge and cladding oxidation, none of which the tool knows about.
  • The boil-off figures assume every joule goes into boiling water already at 100 °C at atmospheric pressure. A pressurised circuit is hotter, and the latent heat is smaller there.
  • The paper’s own event list has the base case’s core damage (35,064 s) slightly before full core uncovery (35,564 s); we used its stated core-damage times as given.

Sources

  • Liu, T., Wu, Z., Bensi, M. and Ma, Z. (2023), A mechanistic model of a PWR-based nuclear power plant in response to external hazard-induced station blackout accidents, Frontiers in Energy Research 11: 1191467, doi:10.3389/fenrg.2023.1191467. Licence CC BY 4.0, stated verbatim on the article page and in the Crossref record, which carries no retraction or correction (both checked 2026-11-24). Values used here: 3,250 MW thermal power; blackout at 100 s; the paper's own Way-Wigner decay-power relation; short-term blackout events at 1.13 h (steam generator dryout), 1.44 h (core uncovery) and 2.49 h (core damage); long-term base case at 7.92, 8.68 and 9.74 h; and core damage at 15.37 h, 12.47 h, 10.71 h and 9.74 h for operating histories of one week, one month, one year and 1,350 effective full-power days.
  • Way-Wigner approximation P/P0 = 0.0622 [t^-0.2 - (t + T)^-0.2] for fission-product decay heat, as given in standard reactor physics textbooks; latent heat of water at 100 °C, 2.257 MJ/kg.