Module 3: Numerical ability · Lesson 3.7 · about 15 min

Time and work, pipes and cisterns

Think in work per day: add rates when people work together, subtract for a leak, and use the LCM trick to avoid fractions. An animated tank, worked examples and practice with fresh numbers.

Key points, meanings and formulas on one page: choose "Save as PDF" in the print box.

Module 3 · about 15 minutes. By the end you will add and subtract rates, handle leaks and people leaving, and use worker-days.

Do not add times; add rates. If A finishes a job in 10 days, A does 1/10 of it each day, and rates of people working together simply add.

1. Rates add

1T=1a+1b−1c
a, b
how long each worker (or filling pipe) takes alone
c
how long a leak (or emptying pipe) takes to undo the whole job: it counts as minus
T
how long they take together
Physical meaning
each one contributes a slice of the job per hour; the slices add up. Together is always faster than the fastest one alone, unless there is a leak.
Two pipes and a drain. Change the times and watch the tank fill; open the drain and it slows down, or never fills.

2. The LCM trick: no fractions

Call the job 36 units (the LCM of 12 and 18). A does 3 units a day, B does 2.
Together for 4 days: 5 × 4 = 20 units done.
16 units are left for B alone: 16 ÷ 2 = 8 more days.
Total time: 4 + 8 = 12 days. Not a single fraction needed.

3. Worker-days

When the number of workers changes, the total work is workers × days (× hours a day, if given). 12 workers × 10 days = 120 worker-days, whoever does them.

“A takes 10 days and B takes 15, so together 12.5 days (the average).” Two people working together must be faster than either alone. Add rates, never average times: the answer is 6 days.

4. Practice

  • Rate = 1/time. Rates add; leaks subtract.
  • Two workers together: ab ÷ (a + b).
  • Use the LCM of the times as the total units to avoid fractions.
  • When workers change: total work = workers × days (× hours).

Check yourself

1A can do a job in 10 days and B in 15 days. Together they take:
2A pipe fills a tank in 4 hours and a leak empties it in 12 hours. With both open, it fills in:
312 workers finish a wall in 10 days. How long would 15 workers take?

Sources

  • National Testing Agency, CUET (UG) syllabus for the General Test (numerical ability) https://cuet.nta.nic.in/ (checked 2026-11-22)
  • Questions: original fibub writing for this course

Your ticks stay in this browser. Save them as a file on the course home.

Updated 2026-11-22. The exam pattern follows the NTA CUET (UG) information bulletin as checked on 2026-11-22: check cuet.nta.nic.in for the current year. fibub is a free independent site, not part of NTA; every question here is original. Practice runs in your browser and nothing you answer is sent anywhere.